Power-cut restart
Restart order after power returns to a sealing cell.
Power-cut restart
This restart card is for the first restart after a power cut in a sealing cell. Plant managers use it to set the release rule, line setters use it at the panel, and maintenance leads use it to record what was reset. Keep it at the wall isolator or control box so the person starting the cell signs before production is released.
Use it after any supply cut that stops a capper, conveyor, induction sealer, steam tunnel, band applicator, camera or reject pocket. It suits sauce, oil, chemical, personal care and nutraceutical lines where a rushed restart can give loose caps, scorched liners, wet sleeves or false rejects. For the sampling record after restart, use the seal check card.
Complete the top boxes first
Start with area, date, shift, product, pack size, neck size, cap, liner or sleeve, and operator name. The supply box comes next: wall isolator reset, voltage steady, no burnt smell, and no breaker left tripped. Then jog the conveyor empty and watch guide rails, transfers and reject pocket movement.
The capping entry comes next. Write the torque recipe or manual setting, cap three bottles, and check that each cap sits square on the bottle land. Record any head pad clean-down or cap chute adjustment done after the outage. Loose caps give poor liner contact; over-tight caps often crease the wad face, scuff the cap top or leave a poor-looking seal after restart.
Prove induction and sleeve settings
Run one capped pack first on a hand-paced unit or the Seal Induction Compact. Write the neck size and foil wad used, then pull the liner back and record the peel result. Once the first pack shows an even bond on the bottle land, release the main conveyor and record the recipe used on the Seal Induction Pro if that is the line sealer.
For tamper sleeves, record sleeve height, bottle spacing, steam ready status and whether bottles entering the sleeve area are dry. Restart the shrink section only after steam is steady and the tunnel has heated through. On Band Shrink 120 cells, watch the first packs for high sleeves, twisted tear lines and wet necks.
Worked filled-in entry
A good entry reads like this: 14:12 supply returned on sauce line one, isolator reset by maintenance, conveyor jogged clear, 38 mm cap and liner confirmed, torque recipe reloaded, three capped bottles checked square. At 14:21 one test bottle was sealed on the compact unit and the liner peeled with an even ring.
The sleeve part continues: steam ready at 14:28, sleeve height reset to the SKU mark, tear line facing the operator, first six sleeves centred after shrink, condensate wiped from guide contact points, reject pocket fired on test trigger, QA released the line at 14:35. The next crew can see who restarted each section, what sample passed, and what time production was released.
Common restart mistakes
The mistake seen most often is switching on every unit at once and then chasing the last alarm shown on the panel. The card forces the order from supply to conveyor, capping, induction, sleeve, inspection and release. Other mistakes are skipping the first peel check, using the previous SKU’s neck size, leaving a partly shrunk sleeve in the tunnel, writing “OK” without a sample time, and ignoring a damp guide. File this card with the batch pack so nuisance rejects, sleeve skew or later cap complaints can be traced back to the exact restart sequence.