Steam start sequence
Cold start sequence for Steam Tunnel S and L.
Steam start sequence
The steam start sequence is a cold start card for setters and fitters bringing a neck-sleeve tunnel back to heat. Use it before the first sleeved bottle enters the chamber after an overnight stop, wash-down, boiler drain or sleeve change. The card fixes the order: water checked, steam purged, pressure settled, dwell set and first pack approved.
Use the same order on Steam Tunnel S for compact narrow-mouth work and on the wider Steam Tunnel L used on large jerries, gallons and other broad-shouldered packs. Where sleeves are placed by Band Shrink 120 or a Band Shrink 240 cell, the card ties applicator settings, bottle spacing and tunnel behaviour into one shift record.
Complete the top lines first
Start with date, shift, operator, SKU, bottle size, cap style and sleeve roll reference. Copy the sleeve’s lay-flat measurement, cut height and tear-line location from the approved sleeve note. Record planned bottle pitch, because tight spacing changes how steam reaches the neck and how much drying time remains.
Tick the start checks in order: main power on, boiler water level visible, clean water used for top-up, drain area clear and chamber guards closed. Write the warm-up start time, then wait for the boiler. Open the steam valve slowly, purge air through the chamber, return to the recipe mark and let pressure settle.
Set sleeve fit, dwell and drying
Confirm that each sleeve sits square to the bottle shoulder, the top edge covers the cap as specified and the tear line presents to the operator position agreed for that SKU. A loose sleeve twists before shrinking; a tight sleeve can grip early and pull the tear line off-centre. Adjust the sleeve feed tray and guides before adding steam.
Dwell is recorded as belt pace through the chamber and the observed shrink result. Run a small group of sleeved bottles at the planned pitch, then check the cap edge, neck, shoulder and perforation. The exit check covers condensate beads, wet shoulders, sleeve scuffing and whether the pack is dry enough for handling after the tunnel.
Worked entry from a jerry line
A completed entry for Steam Tunnel L might read: morning shift, five litre HDPE detergent jerry, wide cap, 45 mm sleeve height, tear perforation facing the handle side, bottle pitch opened by one guide mark. The operator warms the boiler, purges air, returns steam pressure to the saved mark and runs three trial jerries.
The accepted pack has a tight cap band, straight perforation and no standing water on the shoulder after drying. If the next shift reports patchy shrink, maintenance can compare water level, warm-up time, purge step, pressure mark, pitch and drying notes. For steam loss around the chamber, inspect the steam hood seal, drain paths and nozzle faces during the stop.
Mistakes to catch before production
The common errors are rushing boiler warm-up, opening the steam valve hard, skipping the air purge and loading bottles before pressure has settled. Those habits show up as one hot side, one loose side, wrinkled cap edges and random wet packs. Mineral-heavy water adds scale in the boiler and nozzles, then steam delivery changes as the shift warms up.
Fit mistakes are just as visible. Operators often reuse the previous SKU’s sleeve height, ignore a shifted tear perforation, close the bottle pitch after a jam or add steam to fix a sleeve with the wrong lay-flat width. Keep sample bottles, sleeve roll labels and the completed card together so the next start can match the approved pack, not yesterday’s guesswork.