Steam Tunnel L specs
The Steam Tunnel L specs turn into floor checks for large-cap jerry containers and gallon bottles on chemical and oil lines. The rated rate of up to 60 bpm is the finished-pack pace after the sleeve has been placed, with the tunnel doing the final shrink around the cap, neck and upper shoulder.
Start the job by checking whether the site can deliver steady vapour across a broad steam hood, because large caps and tall bands need even heat from front to back. “Wide steam” means a broad hood must feed enough vapour across large caps and tall sleeves. In practice, low steam volume gives loose lower edges, patchy shrink around handles and wet packs at the discharge.
Prepare the site and steam services
Walk the conveyor with the largest container. Confirm straight length for the tunnel body, side access for guide adjustment, room at the exit for wet packs, and a drain route that falls away from the machine. Condensate must exit the hood area instead of dripping back onto soft sleeves.
Fit the steam line with pressure control, isolation, a trap and a drain point maintenance can reach during changeover. Warm up in a fixed order, clear condensate, then feed sample packs. The steam start guide is a useful commissioning checklist for operators and fitters.
Set the mechanical fit
Place a filled sample on the conveyor and check cap diameter, neck height, shoulder width, handle clearance and pack pitch. The container must enter square, stay upright through steam and exit without rubbing the hood. Where the cell needs mounted guides, use the Line Integration Rail to hold the jerry path.
Measure the sleeve before opening steam. Lay-flat width must match the cap and neck, sleeve height must cover the tamper area, and the tear perforation must face the operator or pack instruction side. Use the band sleeve size chart for the measuring route, then prove it on the actual bottle.
Run the first sample
Start with moderate steam pressure, centred guides and enough dwell for the sleeve to pull down without whitening, splitting or climbing. Increase steam in small steps. If hot sleeves touch each other, open the bottle pitch. A jerry with a handle recess may need extra spacing so steam reaches the back of the band.
Run a short sample at production weight. Check the top edge for curl, the bottom edge for loose pockets, the perforation for a clean hand tear and the discharge for condensate trails. Uneven shrink points to guide offset or steam spread. Exit drips call for drain checks and the steam hood seal.
Accept, record and size the job
Accept the Steam Tunnel L when the agreed pack runs at the target pace with square tracking, tight sleeve edges, a clean tear perforation and discharge dry enough for the next coding, labelling or packing step. Record steam pressure, dwell setting, guide width, sleeve height, lay-flat, bottle pitch, drain status and the operator start-up order on the handoff template.
For sizing, send conveyor width and height, available straight length, steam supply details, drain position, target packs per minute, cap dimensions, bottle photos, filled pack weight and sleeve samples or artwork. A short video of current handling around the capper and sleeve station also shows whether bottle pitch is steady enough before the steam hood.
| Model | Steam Tunnel L |
|---|---|
| Rate band | Up to 60 bpm |
| Power / utilities | Wide steam |
| Neck / format | Jerry and gallon |
Parent: Steam Tunnel L.